737-800 COCKPIT project homepage
BUILD LOG

From Plans to Reality

The master chronological record of the project. Each stage has its own dedicated page for technical documentation, photographs and supporting evidence.

BL-001DESIGN / ENGINEERINGCOMPLETED

Initial Cockpit Design

From reference material to a project-specific 737-800 cockpit structure

Open Build Log →
BL-002DESIGN / ENGINEERINGCOMPLETED

MIP Design, Pattern & Verification

Following the initial cockpit design, the Main Instrument Panel (MIP) was developed as a dedicated CAD assembly in Fusion 360. A full-scale physical pattern was then used as an intermediate verification stage before the final manufacturing order, allowing the design to be checked in practice before committing to the final 4 mm aluminium fabrication.

Open Build Log →
BL-003FABRICATION / FINISHINGCOMPLETED

Aluminium MIP — Delivery, Inspection & Painting

The final MIP was received from fabrication in 4 mm aluminium, carefully inspected against the developed design and then prepared and painted before the installation phase.

Open Build Log →
BL-004ASSEMBLY / INSTALLATIONCOMPLETED

MIP Panel & Instrument Installation

With the aluminium MIP painted and ready, the fabricated panels, instruments and associated controls were progressively installed and checked for fit, alignment and integration.

Open Build Log →
BL-005CAD / 3D PRINTINGCOMPLETED

MIP Base Construction, Final Installation & FMC Unit

Display frames for the MIP screens were designed in 3D CAD.

Open Build Log →
BL-0063D PRINTING / FINISHINGCOMPLETED

MIP Display Frame Finishing & Installation

The printed display frames were finished and installed into the MIP.

Open Build Log →
BL-007STRUCTURE / FABRICATION / INSTALLATIONCOMPLETED

First Officer's Sidewall Structure — Fabrication & Installation

Fabrication and installation of the First Officer’s sidewall structure.

Open Build Log →
BL-008STRUCTURECOMPLETED

Main Cockpit Base

The complete cockpit base was constructed as the foundation for the shell and lower structures.

Open Build Log →
BL-009STRUCTURE / ASSEMBLYCOMPLETED

Lower Side Structures

The left and right lower side structures were fabricated, adjusted and installed into the cockpit base.

Open Build Log →
BL-010STRUCTURE / FABRICATIONCOMPLETED

Left Window Frame & Liner

The left window frame and liner were built piece-by-piece. The liner uses MDF skins with a polyurethane foam core, joined with Gorilla Glue, before final installation.

Open Build Log →
BL-011STRUCTURE / ASSEMBLYCOMPLETED

Windshield Construction & Installation

The windshield was constructed piece-by-piece using the same general approach as the left window frame. The construction photos are unfortunately lost; the installation is documented.

Open Build Log →
BL-012FABRICATION / TEST FITCOMPLETED

Cockpit Glareshields, Windshield and Flight Deck Integration

Temporary fitting and alignment of the glareshield wings, No. 1 windshield, Captain-side cockpit window, EFIS and MCP.

Open Build Log →
BL-013FABRICATION / STRUCTURECOMPLETED

Glareshield Final Shaping Preparation & MIP Low Panels

Preparation for the final glareshield shaping, initial MIP low-panel construction and upper glareshield construction before final finishing.

Open Build Log →
BL-014ASSEMBLYCOMPLETED

MIP Low Panels — Fabrication, Finishing & Installation

The two MIP lower panels were fabricated as separate assemblies, finished and installed beneath the Main Instrument Panel with their controls and engraved labels.

Open Build Log →
BL-015FABRICATION / ASSEMBLYCOMPLETED

MIP Low Panels — Construction & Installation

The lower MIP panels were fabricated, finished, fitted with controls and integrated into the MIP.

Open Build Log →